混凝土攪拌機(jī)正常操作時(shí)應(yīng)注意三個(gè)環(huán)節(jié)
攪拌機(jī)運(yùn)行前:混凝土攪拌機(jī)運(yùn)行前、后應(yīng)檢查傳動(dòng)機(jī)構(gòu)、工作裝置、制動(dòng)器等,應(yīng)緊固可靠,確保正常運(yùn)行。大齒圈、皮帶輪等部件應(yīng)加裝防護(hù)罩。攪拌筒的驅(qū)動(dòng)和移動(dòng)部位及所有支撐部位無(wú)異物卡死,倉(cāng)庫(kù)門、斗門、軌道無(wú)異物卡死。
Before mixer operation: before and after concrete mixer operation, check the transmission mechanism, working device, brake, etc., which shall be tight and reliable to ensure normal operation. Large gear ring, pulley and other parts shall be equipped with protective cover. The driving and moving parts of the mixing drum and all supporting parts shall be free of foreign matters, and the warehouse door, hopper door and track shall be free of foreign matters.
中科攪拌機(jī)
Zhongke mixer price
混凝土攪拌機(jī)的正常運(yùn)行是每個(gè)用戶都想看到的,這就要求用戶在使用攪拌機(jī)時(shí)注意以下三個(gè)步驟:
The normal operation of concrete mixer is what every user wants to see, which requires users to pay attention to the following three steps when using the mixer:
1. 攪拌機(jī)運(yùn)行前:混凝土攪拌機(jī)運(yùn)行前后、傳動(dòng)機(jī)構(gòu)、工作裝置、制動(dòng)器等。應(yīng)進(jìn)行可靠的檢查和緊固,以確保正常運(yùn)行。大齒圈、滑輪等部件應(yīng)安裝在防護(hù)罩、攪拌筒、支撐傳動(dòng)及運(yùn)動(dòng)部件上,以及倉(cāng)門、斗門及軌道上不得有異物卡住。
1. Before mixer operation: before and after concrete mixer operation, transmission mechanism, working device, brake, etc. Reliable inspection and fastening shall be carried out to ensure normal operation. Large gear ring, pulley and other parts shall be installed on the protective cover, mixing drum, supporting transmission and moving parts, and there shall be no foreign matters stuck on the bin door, hopper door and track.
2. 攪拌機(jī)正在運(yùn)行:
2. The mixer is running:
(1)喂料時(shí),嚴(yán)禁將頭或手放入料斗和機(jī)架內(nèi)。在操作過(guò)程中,禁止用手、工具或其他物品進(jìn)入攪拌筒內(nèi),進(jìn)行物料的裝卸。
(1) When feeding, it is forbidden to put the head or hand into the hopper and frame. In the process of operation, it is forbidden to use hands, tools or other items to enter the mixing drum for material loading and unloading.
(2)料斗上升時(shí),不要在料斗下工作或行走。料斗的料斗底部要有一個(gè)枕頭,清理料斗時(shí)用鏈條固定。
(2) When the hopper rises, do not work or walk under the hopper. There should be a pillow at the bottom of the hopper, which should be fixed with a chain when cleaning the hopper.
(3)攪拌筒應(yīng)在運(yùn)行中進(jìn)料;只有在攪拌機(jī)中所有的原混凝土全部卸載后才能添加新材料。除反向卸載外,不要在攪拌過(guò)程中停止攪拌,或在滿載時(shí)啟動(dòng)攪拌。
(3) The drum shall be fed in operation; no new material shall be added until all the original concrete in the mixer has been unloaded. Do not stop mixing during mixing or start mixing when fully loaded, except for reverse unloading.
(4)在運(yùn)行過(guò)程中,如故障不能繼續(xù)運(yùn)行,應(yīng)立即切斷電源,清理攪拌筒內(nèi)的混凝土。
(4) In the process of operation, if the fault cannot continue to operate, the power supply shall be cut off immediately and the concrete in the mixing drum shall be cleaned.
3.在攪拌機(jī)的操作:當(dāng)混凝土攪拌完成后或?qū)⑼V钩^(guò)1小時(shí),除了排出剩下的材料,石頭和水也應(yīng)該投入振動(dòng)斗,并打開攪拌機(jī)、清潔的灰漿桶,然后退出。桶內(nèi)不得有積水,以免生銹。同時(shí),應(yīng)混合筒外積聚的粉塵,以保持機(jī)器的清潔和良好狀態(tài)。
3. Operation in the mixer: when the concrete is mixed or will stop for more than 1 hour, in addition to discharging the remaining materials, stones and water should also be put into the vibrating bucket, and the mixer, clean mortar bucket should be opened, and then exit. There shall be no water in the barrel to avoid rust. At the same time, the dust accumulated outside the mixing drum shall be removed to keep the machine clean and in good condition.
以上是中科攪拌機(jī)廠家小編為大家介紹的相關(guān)內(nèi)容,想要了解更多內(nèi)容,歡迎訪問(wèn)網(wǎng)站:http://m.zvmc.cn
The above is the relevant content introduced by the mixer manufacturer of China Science and Technology Co., Ltd. for more information, please visit the website: http://m.zvmc.cn